Church In A Day Timeline:
Wall Raising Kick Off Time 6:35 am
| Wall Raising | 6:35am - 6:45am | 10 min |
| Structure Framing | 6;45am - 7:43am | 1 hr 8 min |
| Wall Sheeting | 6:42am - 7:15am | 32 min |
| Trusses (Roof) | 6:40am - 7:14am | 45 min |
| Roof | 8;35am - 11:10am | 2 hrs 35 min |
| Windows Set | 6:40am - 7:36am | 56 min |
| Rough In Electrical | 6:42am - 2:15pm | 7 hrs 33 min |
| Rough In Plumbing | 7;00am - 11:00am | 3 hrs |
| Front Entry Cover | 7:02am - 7:10am | 8 min |
| Rough In Air | 8:30am - 1:15pm | 4 hrs 45 min |
| Gutter Board | 7:17am - 8:10am | 53 min |
| Roof Decking | 7:20am - 8:20am | 1 hr |
| Overhang | 7:36am - 2:45pm | 7 hrs 9 min |
| Siding | 8:10am - 3:15pm | 7 hrs 5 min |
| Brick | 9:40am - 2:30pm | 4 hrs 50 min |
| Entry Doors | 8:24am - 9:40am | 1 hr 16 min |
| Walls & Ceiling Insulation | 10:40am - 1:30pm | 2 hrs 50 min |
| Sound System Rough | 8:15am - 11:25am | 3 hrs 10 min |
| Drywall Hanging | 11:15 am - 4:00 pm | 3 hrs 10 min |
| Drywall Finish | 12:05 pm - 5:45 pm | 5 hrs 40 min |
| Power onto Building | 1:30 pm | We have power |
| Air-conditioning Units On | 2:00 pm | We have air |
| Landscaping & Flowers | 1:40 pm - 3:00 pm | 1 hr 20 min |
| Drywall Texturing | 3:30 pm - 6:25 pm | 2 hrs 55 min |
| Interior Painting | 5:40 pm - 9:17 pm | 3 hrs 36 min |
| Finish Electrical & Light Fixtures | 5:15 pm - 12:50 am | 7 hrs 35 min |
| Heat & Air Conditioning | 9;30 pm - 12:05 am | 2 hrs 35 min |
| Finished Plumbing | 9:00 pm - 12:00 am | 3 hrs 10 min |
| Interior Trim | 5:00 pm - 7:37 pm | 2 hrs 37 min |
| Sound System Finish | 12:00 am - 3:00 am | 3 hrs |
| Floor Coverings | 9:30 pm - 2:30 am | 5 hrs 40 min |
| Finish Hardware & RR Partitions | 9:30 pm - 12:00 am | 2 hrs 30 min |
| Finish Interior Cleaning | 8:30 pm - 1:00 am | 8 hrs 30 min |
| Church Pews & Furniture | 1:05 am - 1:35 am | 30 min |
| Guttering & Downspouts | 4:00 pm - 5:12 pm | 1 hr 12 min |
| Punch Out Detail | 7:00 am - 9:00 am | 2 hrs |
Key Construction Points
| From Framing Kickoff To Drywall Hanging | 4 hrs 45 min |
| From Framing Start To Drywall Finish | 6 hrs 30 min |
| From Framing To Roof Completion | 5 hrs 45 min |
| From Framing Start To Exterior Building Finish | 9 hrs 10 min |
| From Framing To All Rough Inside Inspections Release | 4 hrs 35 min |
| From Framing Start To Interior Paint Completion | 14 hrs 50 min |
| From Framing Start To Drywall Texture Start | 9 hrs 35 min |
| Air Conditioning to Building 1:30 pm | 7 hrs 55 min |
| Total Construction - Start to Finish 2:30 am | 19 hours |
Please Note: This project was completed on a beautiful day with few technical complications. Not all projects are accomplished this quickly.